Seventeen years ago, in order to effectively control the SARS epidemic, Beijing built Xiaotangshan Hospital in seven days, setting a world record for the speed of hospital construction. 17 years later, the renovation project of Xiaotangshan Hospital started. The reporter learned that at present, all the medical equipment of Xiaotangshan Hospital has been in place, and the last batch of medical equipment has been tested on site. At 10 a.m. on March 16, more than 20 staff members of Beijing Metrology Institute went to Xiaotangshan Hospital again.
CT machine, electrocardiograph, defibrillator... Although there are not many instruments in a room, there are one or two staff members beside each instrument“ Take this equipment room for example. There are three sets of equipment. Do not look at the three devices, in fact, across the professional, need three different professional staff to test The director of the market and customer relationship Department of the Municipal Institute of Metrology explained authoritatively that the ultra pure water machine, ultra clean worktable and centrifuge all need different professional and technical personnel to "handle".
"At present, all the medical equipment of Xiaotangshan Hospital has been in place. This is our sixth time to test, and it is also the last batch of on-site medical equipment to be tested in Xiaotangshan Hospital. " On February 10, the municipal Metrology Institute received the task of Metrology and testing of diagnosis and treatment equipment in Xiaotangshan Hospital. Since February 11, five professional staff have been to Xiaotangshan Hospital for on-site testing six times, and 870 pieces of equipment have been tested.
"No matter how late it is, we will ensure that all the on-site equipment of Xiaotangshan Hospital will be tested today." Yao Hejun, President of the Municipal Institute of metrology, told reporters that today, about 900 instruments and equipment are expected to be tested. In addition to professional medical instruments, even refrigerators in hospitals are not allowed to pass.
In addition to the equipment to be tested on site, some instruments and equipment such as electronic thermometer and sphygmomanometer must be taken back to the laboratory for testing. Wu Jian, director of the temperature and humidity laboratory of the Institute of thermal flow and process science of the Municipal Institute of metrology, told the reporter that the electronic thermometer must be placed in the constant temperature equipment for detection, and the detection temperature is 37 ℃ and 41 ℃ respectively“ For the instruments and equipment that have been tested in the past 10 working days, now we work overtime to ensure that they must be tested within 24 hours and sent back to Xiaotangshan Hospital immediately. ".
"At present, hundreds of electronic thermometers have been tested, and the error of most thermometers is about 0.1 degrees, which meets the standard. However, more than a dozen electronic thermometers are faulty and have been returned. " Authorities said that in addition to the failure of the electronic thermometer, the unqualified electronic sphygmomanometer was also detected. All the equipment with incomplete functions and substandard values have been marked and returned“ Many instruments and equipment may not be accurate when they leave the factory. They must be measured to eliminate the inaccurate equipment. "
In the past, all hospitals needed to send medical equipment for inspection if they wanted to test it“ Now, during the epidemic period, the hospital itself is short of manpower, so we have launched a "door-to-door pick-up and delivery" service. Even if there is only one thermometer, we will go to the hospital to pick it up and send it back to the hospital after testing. " Yao Hejun said that in the next step, if the hospital has new medical instruments and equipment that need to be tested, there will be demand and testing at any time.